§ 1.482-7(g)(5)(iv) Best method analysis considerations.

« | »

The comparability and reliability considerations stated in § 1.482-4(c)(2) apply. Consistent with those considerations, the reliability of applying the acquisition price method as a measure of the arm’s length charge for the PCT Payment normally is reduced if –

(A) A substantial portion of the target’s nonroutine contributions to the PCT Payee’s business activities is not required to be covered by a PCT or group of PCTs, and that portion of the nonroutine contributions cannot reliably be valued;

(B) A substantial portion of the target’s assets consists of tangible property that cannot reliably be valued; or

(C) The date on which the target is acquired and the date of the PCT are not contemporaneous.